Work Schedule

Time Line  –  January 2018

January — Get contractors and estimates for all aspects of renovation. Finish the business plan. Remove old staircase.

February — Pour concrete foundation pads in the basement. Purchase supplies. Talk to our business adviser and prepare bank loan

March — House inspections for loan. Apply for loan. Excavate on east side. Build utility shed. Electrical and water lines. Rebuild stairs

 April — Excavate on west side. Septic system. Pour basement concrete. Lift the perimeter beam for moisture break. Hook up electrical meters, water pump and pressure tank.

May —  Moisture wicking matt, metal studs, insulation and finish on basement walls. Main staircase.

June — Windows, siding, plumbing, electrical wiring, heating system. Frame fire exit and extension.

July —  Interior framing, complete plumbing.

August  — Aircrete insulation

September — Sheetrock, finish flooring, tile work, painting

October — Kitchen cabinets, appliances

November — Advertise, test renters.

December — Sign rental leases, begin making payments on bank loan.